PROJECT OVERVIEW

Right First Time Engineering was contracted by Nairobi bottlers limited to install and commission a state-of-the-art hot fill line at their production facility. This project required precision engineering to ensure seamless integration with existing production systems while meeting the highest standards of food safety and operational efficiency.

The installation encompassed the full mechanical and electrical setup of hot filling equipment, including high-temperature filling heads, pasteurization tunnels, and automated capping systems. Our team delivered a turnkey solution that significantly boosted the facility's hot-fill production capacity.

KEY DELIVERABLES:

  • Installation of high-temperature filling and capping equipment.
  • Integration of pasteurization tunnel systems.
  • Full electrical wiring and PLC-based control system setup.
  • Mechanical piping and utility connections.
  • Commissioning, testing, and operator training.

Project Details

Client Nairobi bottlers limited
Sector Brewing & Beverage
Duration 4 Months
Value Confidential